Project Title: Eltham College Turberville Building
location: Grove Park Road | Mottingham | LONDON
Completed: January 2019
Client: Eltham College
Project Manager: Bristow Johnson
Quantity Surveyor: Bristow Johnson
Architect: Levitt Bernstein
Structural Engineer: Morgan Tucker
Services Engineer: Crofton
Project Value: £10million
The Eltham College project included the demolition of the existing and surrounding buildings to allow for a new build teaching facility, including a sixth form centre.
Works included piled foundations, cross wall construction, twin wall precast concrete frame, structural steelwork and exposed fair faced concrete classrooms. The works also comprised external landscaping and were carried out adjacent to the live school environment.